26. The public body evaluates the tenders received, ensuring that the tenderers are eligible and their tenders are compliant.
Despite the foregoing, where the tender documents provide for compliance tests, the tests are first carried out in respect of the goods proposed by the tenderer who, in the absence of those tests, would be the successful tenderer. The tests are then carried out in respect of the goods proposed by the next tenderer only if the goods proposed by the preceding tenderer fail the compliance tests and so forth until the tests are successful. However, in the case of a delivery order contract entered into with a number of suppliers, the compliance tests are carried out in respect of the goods proposed by all the tenderers who, in the absence of those tests, would be retained.
If the public body rejects a tender because it is not compliant or because the tenderer is ineligible, the public body so informs the tenderer by indicating the reason for rejection not later than 15 days after the contract is awarded. However, if rejection takes place at the first stage of a call for tenders involving more than one stage, the public body so informs the tenderer at the time an invitation to take part in the next stage is sent to the selected providers.
A tender received after the closing date and time for receiving tenders may not, for that sole reason, be considered non-compliant if the delay is attributable solely to the public body.
O.C. 295-2016, s. 26; S.Q. 2018, c. 10, s. 32.
26. The public body evaluates the tenders received, ensuring that the tenderers are eligible and their tenders are compliant.
Despite the foregoing, where the tender documents provide for compliance tests, the tests are first carried out in respect of the goods proposed by the tenderer who, in the absence of those tests, would be the successful tenderer. The tests are then carried out in respect of the goods proposed by the next tenderer only if the goods proposed by the preceding tenderer fail the compliance tests and so forth until the tests are successful. However, in the case of a delivery order contract entered into with a number of suppliers, the compliance tests are carried out in respect of the goods proposed by all the tenderers who, in the absence of those tests, would be retained.
If the public body rejects a tender because it is not compliant or because the tenderer is ineligible, the public body so informs the tenderer by indicating the reason for rejection not later than 15 days after the contract is awarded. However, if rejection takes place at the first stage of a call for tenders involving more than one stage, the public body so informs the tenderer at the time an invitation to take part in the next stage is sent to the selected providers.
O.C. 295-2016, s. 26.
In force: 2016-06-01
26. The public body evaluates the tenders received, ensuring that the tenderers are eligible and their tenders are compliant.
Despite the foregoing, where the tender documents provide for compliance tests, the tests are first carried out in respect of the goods proposed by the tenderer who, in the absence of those tests, would be the successful tenderer. The tests are then carried out in respect of the goods proposed by the next tenderer only if the goods proposed by the preceding tenderer fail the compliance tests and so forth until the tests are successful. However, in the case of a delivery order contract entered into with a number of suppliers, the compliance tests are carried out in respect of the goods proposed by all the tenderers who, in the absence of those tests, would be retained.
If the public body rejects a tender because it is not compliant or because the tenderer is ineligible, the public body so informs the tenderer by indicating the reason for rejection not later than 15 days after the contract is awarded. However, if rejection takes place at the first stage of a call for tenders involving more than one stage, the public body so informs the tenderer at the time an invitation to take part in the next stage is sent to the selected providers.
O.C. 295-2016, s. 26.